C.R.S. Section 40-4-101
Regulations, service, and facilities prescribed


(1)

Whenever the commission, after a hearing upon its own motion or upon complaint, finds that the rules, regulations, practices, equipment, facilities, or service of any public utility or the methods of manufacture, distribution, transmission, storage, or supply employed by it are unjust, unreasonable, unsafe, improper, inadequate, or insufficient, the commission shall determine the just, reasonable, safe, proper, adequate, or sufficient rules, regulations, practices, equipment, facilities, service, or methods to be observed, furnished, constructed, enforced, or employed and shall fix the same by its order, rule, or regulation.

(2)

The commission shall prescribe rules and regulations for the performance of any service or the furnishing of any commodity of the character furnished or supplied by any public utility, and upon proper tender of rates, such public utility shall furnish such commodity or render such service within the time and upon the conditions provided in such rules.

(3)

The commission shall prescribe rules and regulations for the termination of gas and electric service to residential customers. Said rules and regulations shall require that the customer be given reasonable notice and an opportunity to be heard by the terminating utility company before termination of gas or electric service and that such service may not be terminated during certain periods if the customer establishes that termination of the service would be especially dangerous to the health or safety of the customer and that he is unable to pay for the service as regularly billed by the utility, or that he is able to pay but only in reasonable installments.

Source: Section 40-4-101 — Regulations, service, and facilities prescribed, https://leg.­colorado.­gov/sites/default/files/images/olls/crs2023-title-40.­pdf (accessed Oct. 20, 2023).

Green check means up to date. Up to date

Current through Fall 2024

§ 40-4-101’s source at colorado​.gov