C.R.S. Section 9-5-106
Implementation plan


The builder of any project regulated by this article shall create an implementation plan that guarantees the timely and evenly phased delivery of the required number of accessible units. Such plan shall clearly specify the number and type of units required and the order in which they are to be completed. Such implementation plan shall be subject to approval by the entity with enforcement authority in such project’s jurisdiction. The implementation plan shall not be approved if more than thirty percent of the project is intended to be completed without providing a portion of accessible units required by section 9-5-105; except that, if an undue hardship can be demonstrated, or other guarantees provided are deemed sufficient, the jurisdiction having responsibility for enforcement may grant exceptions to this requirement. The implementation plan shall be approved by the governmental unit responsible for enforcement before a building permit is issued.

Source: Section 9-5-106 — Implementation plan, https://leg.­colorado.­gov/sites/default/files/images/olls/crs2023-title-09.­pdf (accessed Oct. 20, 2023).

Green check means up to date. Up to date

Current through Fall 2024

§ 9-5-106’s source at colorado​.gov