C.R.S. Section 24-92-103
Construction of public projects

  • invitation for bids

(1)

All construction contracts for public projects that do not receive federal moneys may be solicited by invitation for bids pursuant to this section.

(2)

An invitation for bids shall be issued and shall include a project description and all contractual terms and conditions applicable to the public project.

(3)

Adequate public notice of the invitation for bids shall be given at least fourteen days prior to the date set forth therein for the opening of bids, pursuant to rules. Such notice may include publication by electronic online access pursuant to section 24-92-104.5 or in a newspaper of general circulation at least fourteen days prior to bid opening or in an electronic medium approved by the executive director of the department of personnel.

(4)

Bids shall be opened publicly in the presence of one or more witnesses at the time and place designated in the invitation for bids. The amount of each bid and such other relevant information as may be specified by rules, together with the name of each bidder, shall be entered on a record, and the record shall be open to public inspection. After the time of the award, all bids and bid documents shall be open to public inspection in accordance with the provisions of sections 24-72-203 and 24-72-204.

(5)

Bids shall be unconditionally accepted, except as authorized by subsection (7) of this section. Bids shall be evaluated based on the requirements set forth in the invitation for bids, which may include criteria to determine acceptability, such as inspection, testing, quality, workmanship, delivery, and suitability for a particular purpose. Those criteria that will affect the bid price and be considered in the evaluation for award shall be objectively measurable, such as discounts, transportation costs, and total or life-cycle costs.

(6)

Withdrawal of inadvertently erroneous bids before the award may be permitted pursuant to rules if the bidder submits proof of evidentiary value which clearly and convincingly demonstrates that an error was made. Except as otherwise provided by rules, all decisions to permit the withdrawal of bids based on such bid mistakes shall be supported by a written determination made by the responsible officer.

(7)

The contract shall be awarded with reasonable promptness by written notice to the low responsible bidder whose bid meets the requirements and criteria set forth in the invitation for bids. In the event that all bids for a construction project exceed available funds, as certified by the appropriate fiscal officer, the responsible officer is authorized, in situations where time or economic considerations preclude resolicitation of work of a reduced scope, to negotiate an adjustment of the bid price with the low responsible bidder in order to bring the bid within the amount of available funds; except that the functional specifications integral to completion of the project may not be reduced in scope, taking into account the project plan, design, and specifications and quality of materials.

Source: Section 24-92-103 — Construction of public projects - invitation for bids, https://leg.­colorado.­gov/sites/default/files/images/olls/crs2023-title-24.­pdf (accessed Oct. 20, 2023).

24‑92‑101
Short title
24‑92‑102
Definitions
24‑92‑103
Construction of public projects - invitation for bids
24‑92‑103.5
Construction of public projects - invitation for best value bids
24‑92‑103.7
Disclosure - invitation for bids - invitation for best value bids
24‑92‑104
Exemptions - applicability
24‑92‑104.5
Solicitation of bids by electronic online access - department of transportation
24‑92‑105
Cancellation of invitations for bids
24‑92‑106
Responsibility of bidders and offerors
24‑92‑107
Prequalification of contractors
24‑92‑108
Types of contracts
24‑92‑109
Agency of government to submit cost estimate
24‑92‑110
Rules and regulations
24‑92‑111
Audit
24‑92‑112
Finality of determinations
24‑92‑113
Reporting of anticompetitive practices
24‑92‑114
Prohibition of dividing work of public project
24‑92‑115
Apprenticeship utilization requirements - mechanical, electrical, and plumbing contracts - public projects - definition
24‑92‑116
Department of transportation - reporting requirements
24‑92‑117
Maximum global warming potential for materials used in eligible projects - buildings - projects that are not roads, highways, or bridges - environmental product declaration - short title - report - definitions
24‑92‑118
Maximum global warming potential for materials used in public projects - road - highway - bridge projects - environmental product declaration - short title - report - definitions
24‑92‑201
Definitions
24‑92‑202
Contractors subject to provisions - weekly payment of employees - rules
24‑92‑203
Prevailing rate of wages and other payments - specifications in solicitations and contract - repeal
24‑92‑204
Specification in contract - payment of wages - amount and frequency - unclaimed prevailing wages special trust fund - creation
24‑92‑205
Investigation and determination of prevailing wages - filing of schedule - repeal
24‑92‑206
Statutory provisions included in contracts
24‑92‑207
Prevailing wage rates - posting
24‑92‑208
Apprenticeship contribution rate
24‑92‑209
Enforcement - rules
24‑92‑210
Private right of action to collect wages or benefits - definition
24‑92‑301
Short title
24‑92‑302
Legislative declaration
24‑92‑303
Definitions
24‑92‑304
Energy sector public works projects - craft labor employment - training - wage requirements
24‑92‑305
Energy sector public works projects - record keeping - reporting - craft labor certification - sanctions - compliance with best value employment metrics
24‑92‑306
Energy sector public works projects - use of project labor agreements
24‑92‑307
Energy sector public works projects - existing authority of the public utilities commission
Green check means up to date. Up to date

Current through Fall 2024

§ 24-92-103’s source at colorado​.gov