C.R.S. Section 32-9-119.1
Transportation expansion plan

  • utility relocation
  • legislative declaration
  • definitions

(1)

The general assembly hereby finds and declares that:

(a)

The district has been authorized to construct a transportation expansion plan adopted by the board and approved by the voters on November 2, 2004. The transportation expansion plan anticipates that construction will be completed on all fixed guideway corridors in a twelve-year period.

(b)

The scheduling and timely performance of the transportation expansion plan partially depends on coordination with utility companies for the prompt performance of utility relocation work necessitated by construction of the transportation expansion plan.

(c)

Increased coordination between the district and utility companies is in the public interest, and prompt performance of utility relocation work within the adopted plan schedule will reduce delays and costs of construction. Utility relocation work shall be undertaken in a manner that minimizes the relocation cost and the disruption of utility services.

(2)

Intentionally left blank —Ed.

(a)

The district shall negotiate with any affected utility company in each fixed guideway corridor. In coordination with the district, each utility company shall determine whether a district contractor or the utility company shall be responsible for the relocation of its utility facilities. In making such a determination, the utility company shall take into consideration the location of the utility facilities, complexity of the relocation, and timing of the need for relocation work.

(b)

The district and the utility company shall make such arrangements for funding utility relocations as are specified in the easements, licenses, franchises, or other property interests and rights of use held by the district or the utility company. Nothing in this section is intended to alter existing property agreements, licenses, or other interests of the district and utility company regarding the obligation to pay for utility relocation.

(3)

Intentionally left blank —Ed.

(a)

The district may enter into fixed guideway corridor utility relocation agreements with a utility company. Such agreements shall be for the performance of all services required to assure timely relocation of utilities according to the most current written standards and practices established by the utility company at the time the agreement is entered into, unless other standards are mutually selected by the district and the utility company.

(b)

A fixed guideway corridor utility relocation agreement shall include a schedule for design, review, dispute resolution, and construction.

(c)

Intentionally left blank —Ed.

(I)

A fixed guideway corridor utility relocation agreement may provide for a utility company betterment, including, but not limited to, increased capacity and extensions of services; except that a betterment shall not materially delay project construction and shall be at the expense of the utility company.

(II)

As used in this section, “betterment” means any upgrade of the utility facility being relocated that is not attributable to project construction and is made solely for the benefit of and at the election of the utility.

(d)

A fixed guideway corridor utility relocation agreement may incorporate reasonable and appropriate conditions, including, but not limited to, conditions for ensuring:

(I)

The prompt performance of utility relocation work by either the district, utility company, or contractor for the transportation expansion plan, as specified in the agreement;

(II)

The cooperation of the utility company with the contractor for the transportation expansion plan; and

(III)

The payment by the utility company of any damages caused by the company’s delay in the performance of the relocation work or interference with the performance of the project by any other contractor, except when such delay or interference is caused by a force majeure.

(4)

All design and construction of utility relocation shall be subject to review and approval by district and utility company engineers.

(5)

Intentionally left blank —Ed.

(a)

If the district and utility company are unable to reach a fixed guideway corridor utility relocation agreement, or if utility relocation disputes arise under an agreement, the district and utility company shall each designate an official, at no level lower than district corridor project manager and utility company chief engineer, to resolve the differences.

(b)

If the differences cannot be resolved pursuant to paragraph (a) of this subsection (5), utility relocation disputes shall be heard in the following district courts for each of the following corridors and projects:

(I)

For union station, Denver county district court;

(II)

For the U.S. 36 corridor, Boulder county district court;

(III)

For the west corridor, Jefferson county district court;

(IV)

For the gold line corridor, Jefferson county district court;

(V)

For the east corridor, Denver county district court;

(VI)

For the I-225 corridor, Arapahoe county district court;

(VII)

For the southwest corridor, Arapahoe county district court; and

(VIII)

For the north corridor, Adams county district court.

(c)

It shall be presumed that there will be irreparable harm to the public if an injunction is not granted to require utility relocation, regardless of a later determination as to which party is responsible for the cost of relocation.

(6)

Intentionally left blank —Ed.

(a)

The district shall provide a utility company with detailed maps, drawings, plans, and profiles of the district’s proposed improvements in each fixed guideway corridor in the transportation expansion plan at:

(I)

The conclusion of preliminary engineering;

(II)

Sixty percent completion of final design;

(III)

The conclusion of final design; and

(IV)

Such other times as may be requested by the utility company.

(b)

The district shall solicit information as to the location of utility facilities within the fixed guideway corridor from the utility company.

(c)

For all utilities identified on any documents provided to or in the possession of the district, the district shall provide written notice to a utility company as soon as practicable of a transportation expansion plan that will require the relocation of the company’s facilities.

(d)

Intentionally left blank —Ed.

(I)

Where documents have been in the possession of the district during final design of a fixed guideway corridor, the district shall provide notice to a utility company of a transportation expansion plan that will require the relocation of the company’s facilities not later than one year before relocation is required for each relocation on each fixed guideway corridor.

(II)

Notwithstanding subparagraph (I) of this paragraph (d), if major electrical facilities must be relocated, the district shall provide notice to a utility company at least eighteen months in advance of the required relocation date or the district shall pay the cost of any temporary relocation measures required to maintain service to utility customers. If temporary relocation measures are necessary, such measures shall be provided at the lowest possible cost during construction and relocation.

(III)

For any discovery of utilities during construction that are not identified on documents provided to or in possession of the district, the district and the utility company shall confer within forty-eight hours of discovery to determine appropriate relocation procedures.

(IV)

The district and utility company shall, within ten days of discovery, enter into an agreement as to the manner in which any necessary relocation will be accomplished and the party that shall perform the work.

(V)

If an agreement is reached and if the utility company performs under the agreement, the utility company shall not be liable for delay damages as provided in subsection (8) of this section.

(7)

Intentionally left blank —Ed.

(a)

For purposes of ensuring continuation of required utility services to the residents of the district during and after construction of the fixed guideway corridors, the district may provide, and condemn when necessary, replacement easements for the relocation of utilities. If such replacement easements are necessary, the district shall endeavor to meet any existing standards of the utility for easements. Any necessary condemnation shall be considered a transportation project undertaken by the district. The cost of replacement easements shall be paid:

(I)

By the district in those instances where the district has acquired, at no extra cost, an easement previously owned and occupied by the utility; or

(II)

By the utility if the district has compensated the utility for a previously occupied easement from which the utility is being relocated.

(b)

Notwithstanding any local law to the contrary, aboveground utility facilities shall be relocated aboveground and underground utility facilities shall be relocated underground. To minimize the cost of the reconfiguration of the utility facility, the replacement easement shall be acquired as close as possible to the original location of the facility that must be relocated.

(8)

Intentionally left blank —Ed.

(a)

Where the utility company has elected to perform relocation work or where there has been no agreement reached between a utility company and the district, the utility company shall be liable to the district for actual damages suffered by the district as a direct result of the utility company’s delay in the performance of any utility relocation work or as a direct result of the utility company’s interference with the performance of fixed guideway corridor construction by other contractors.

(b)

Notwithstanding paragraph (a) of this subsection (8), a utility company shall not be liable for damages caused by the failure to timely perform the relocation work or the interference with the performance of the transportation expansion plan by another contractor when the failure to perform or the interference is caused by a force majeure.

Source: Section 32-9-119.1 — Transportation expansion plan - utility relocation - legislative declaration - definitions, https://leg.­colorado.­gov/sites/default/files/images/olls/crs2023-title-32.­pdf (accessed Oct. 20, 2023).

32‑9‑101
Short title
32‑9‑102
Legislative declaration
32‑9‑103
Definitions
32‑9‑104
Liberal construction
32‑9‑105
Creation of district
32‑9‑106.1
District area
32‑9‑106.6
Additional district areas as a result of annexation
32‑9‑106.7
Additional district area - petition or election - required filings - definitions
32‑9‑106.8
Additional district areas - annexation of unincorporated territory that is entirely surrounded by the district
32‑9‑106.9
District area - town of Castle Rock in Douglas county
32‑9‑107
Mass transportation system
32‑9‑107.5
Regional fixed guideway mass transit system - authorization
32‑9‑107.7
Regional fixed guideway mass transit systems - construction - authorization
32‑9‑109.5
Board of directors - membership - powers
32‑9‑111
Election of directors - dates - terms
32‑9‑112
Vacancies - appointments - recall
32‑9‑113
Fidelity bonds
32‑9‑114
Board’s administrative powers
32‑9‑115
Records of board - audits
32‑9‑116
Meetings of board
32‑9‑117
Compensation of directors
32‑9‑118
Conflicts in interest prohibited
32‑9‑119
Additional powers of district
32‑9‑119.1
Transportation expansion plan - utility relocation - legislative declaration - definitions
32‑9‑119.3
Elections for sales tax rate increase
32‑9‑119.4
Election for a sales tax rate increase - petition requirement
32‑9‑119.5
Competition to provide vehicular service within the regional transportation district - definition
32‑9‑119.7
Cost efficiency of transit services - reporting - plans
32‑9‑119.8
Provision of retail and commercial goods and services at district transfer facilities - residential and other uses at district transfer facilities permitted - definitions
32‑9‑119.9
Limited authority to charge fees for parking - reserved parking spaces - penalties - definitions
32‑9‑120
Levy of taxes - limitations
32‑9‑121
Levies to cover deficiencies
32‑9‑122
Levying and collecting taxes - lien
32‑9‑123
Delinquent taxes
32‑9‑123.5
Prohibition on borrowing by district
32‑9‑124
Forms of borrowing
32‑9‑125
Issuance of notes
32‑9‑126
Issuance of warrants
32‑9‑127
Maturities of notes and warrants
32‑9‑128
Incurrence of special obligations
32‑9‑128.5
Private activity and exempt facility bonds
32‑9‑129
Issuance of temporary bonds
32‑9‑130
Issuance of interim notes
32‑9‑131
Pledge of proceeds of sales taxes and revenues
32‑9‑132
Ranking among different issues
32‑9‑133
Ranking in same issue
32‑9‑134
Payment recital in securities
32‑9‑135
Incontestable recital in securities
32‑9‑136
Limitation upon payment
32‑9‑137
Security details
32‑9‑138
Negotiability
32‑9‑139
Single bonds
32‑9‑140
Sale of securities
32‑9‑141
Application of proceeds
32‑9‑142
Use of unexpended proceeds
32‑9‑143
Covenants in security proceedings
32‑9‑144
Remedies of security holders
32‑9‑145
Limitations upon liabilities
32‑9‑146
Interest after maturity
32‑9‑147
Refunding bonds
32‑9‑148
Issuance of interim notes
32‑9‑149
Elections
32‑9‑150
Election resolution
32‑9‑151
Conduct and costs of elections
32‑9‑156
District - tax exempted
32‑9‑158
Merger, consolidation, or assumption of district
32‑9‑159
Freedom from judicial process
32‑9‑160
Misdemeanors
32‑9‑161
Eminent domain
32‑9‑162
Money management
32‑9‑163
Investment management
32‑9‑164
Custodians
Green check means up to date. Up to date

Current through Fall 2024

§ 32-9-119.1’s source at colorado​.gov